Deeper Demolition
Existing interior materials and selected hardscape are removed so the pool and surrounding area can be rebuilt as a coordinated system.
A complete homeowner guide to what happens when a pool remodel includes interior demolition, surrounding hardscape removal, new plumbing, masonry, decking, interior finish, startup and first-month care.
A full remodel is more involved than a basic resurfacing project. This guide explains the typical construction sequence, the activity you may see on-site, the homeowner responsibilities that matter most, and the conditions that can affect the schedule.
A full pool remodel typically reaches beyond tile and interior finish. Depending on the contracted scope, it may also include removal of the surrounding deck, replacement of underground plumbing, new coping and masonry, drainage and grading work, and installation of new hardscape.
Existing interior materials and selected hardscape are removed so the pool and surrounding area can be rebuilt as a coordinated system.
Main drains, skimmers, returns and water-feature lines can be replaced and pressure-tested before trenches are backfilled.
Tile, coping, masonry, grading and hardscape are installed to create a more cohesive finished pool and outdoor-living environment.
Full remodels involve more trades, more material movement and more activity around the property. A few early preparations help reduce delays and protect the site.
Finalize tile, coping, veneer and hardscape selections early enough to accommodate ordering and lead times.
Keep gates, side yards and staging areas clear. Remove fragile decorations, furniture and items that could interfere with access.
Demolition, excavation, concrete work and material delivery can be loud. Keep children and pets away from active work areas.
Depending on the scope and jurisdiction, permits, inspections, utility coordination or additional site preparation may be required.
The full remodel begins by draining the existing pool. Our team places a submersible pump in the deep end and routes a discharge hose to the nearest suitable sanitary clean-out.
The pool equipment and automatic fill are shut off, and the water level begins to drop. The discharge system should remain undisturbed.
Usually started the day before demolition or preparation work begins.
Once the pool is empty, relief holes are drilled in the pool floor to relieve underground pressure. The existing interior finish and tile are then removed. Coping and other masonry are also removed when included in the contracted scope.
Jackhammers and demolition equipment create significant noise and activity. Debris is collected and hauled away as work progresses.
Approximately two to four days, depending on pool size, access and site conditions.
Existing concrete, pavers or other deck materials included in the scope are broken up, removed and hauled away. Larger equipment may be used when site access allows; narrow-access properties typically require smaller equipment and more hand work.
This phase can involve skid steers, excavators, breakers, trucks and active debris removal. Expect noise, dust and frequent movement through the designated access route.
Approximately two to five days, depending on the amount of hardscape, material thickness and site access.
The pool shell is core-drilled as needed so the plumbing included in the project can be replaced. This may include main drains, skimmers, return lines, cleaner lines and water-feature plumbing.
Trenches and an organized network of PVC lines will be visible around the pool. The lines are pressure-tested as a critical quality control step before they are permanently covered.
Approximately two to four days for a complete plumbing replacement, depending on the scope and equipment layout.
With demolition and underground work substantially complete, the decorative masonry begins. Waterline tile, coping, veneer stone, raised walls and other contracted masonry features are carefully laid out and installed.
Skilled masons set each tile and stone with careful attention to alignment, transitions and finished elevations. The pool begins to show its final character during this stage.
Approximately two to seven days, depending on material selections, layout complexity and the amount of masonry included.
After underground work is complete, plumbing trenches are carefully backfilled and the surrounding area is regraded. The base is then prepared for the contracted concrete, pavers, natural stone, walkways or other hardscape features.
Concrete trucks, material pallets, compacting equipment and finishing crews may be on-site. The yard begins changing from an active construction zone into a cohesive finished environment.
Approximately five to ten days, depending on hardscape scope, material, access, curing requirements and weather.
The selected plaster or pebble finish is mixed, applied and hand-troweled by a specialized finishing crew. This is the interior surface you will see and feel every time you use the pool.
The application is completed during a coordinated installation. For pebble finishes, the crew normally returns the following morning to acid-wash, clean and expose the aggregate.
One day for the initial application, followed by the appropriate cleaning, acid-wash and pool-filling sequence.
A freshly applied pebble finish can look hazy, chalky, uneven or imperfect while it is dry. You may notice pinholes, minor surface variations, trowel marks or areas where fewer pebbles appear exposed.
That first-day appearance is not the finished result and should not be judged before the next cleaning step and water fill.
The finishing crew returns to acid-wash and clean the surface. They expose the pebble, remove haze and residue, and fill or address small holes and minor imperfections where needed.
Most minor visual concerns improve substantially after the acid wash and become much less noticeable once the pool is full of water.
Once the pool is full, a CPO-certified pool service company should complete the startup. The service company begins balancing the water, follows the applicable startup procedure and explains the early-care requirements.
Water chemistry is managed carefully while the new finish cures. Plaster dust may continue appearing during the early days and must be removed through proper brushing and filtration.
Startup begins after the pool is filled and continues through the initial curing and water-balancing period.
Proper brushing is one of the most important things the homeowner can do to help a new plaster or pebble finish cure and develop correctly.
Unless your written agreement states otherwise, brushing the new interior finish is the homeowner’s responsibility. Brush the walls, floor, steps, benches and corners twice daily during the first 14 days.
Brushing removes plaster dust, helps the finish cure more evenly and assists with exposing the pebble aggregate.
Pay special attention to areas that appear smoother or where fewer pebbles are visible.
Continue brushing the entire pool—not only the areas that look different. Consistent brushing helps create a more uniform final appearance.
Do not stop the water once filling begins. Continue until the water reaches the middle of the tile line.
Brush all interior surfaces twice daily for the first 14 days. Brushing is critical and is the homeowner’s responsibility.
Do not turn on the pool heater during the first 28 days while the finish is curing.
Do not add salt for at least 30 days. PLAPCO recommends waiting approximately 90 days.
Maintain balanced water chemistry to protect the finish, tile, coping and surrounding masonry.
Clean filters and service the equipment based on use, debris load and the equipment manufacturer’s recommendations.
The timing shown throughout this guide is general. Some phases overlap, while others must wait for inspections, curing, material delivery or completion of the previous trade.
Shell damage, unsuitable soil, deteriorated plumbing or buried obstacles may not be visible until demolition begins.
Rain, extreme temperatures and wet site conditions can delay demolition, concrete, masonry, finish work and curing.
Special-order tile, coping, stone and pavers may have changing lead times or availability.
When required, inspections and coordination with utilities or other professionals can affect when the next phase begins.
See the shorter remodel sequence for projects that do not include a complete hardscape and plumbing replacement.
View the Pool Remodel Guide → Pool RemodelingLearn more about interior finishes, tile, coping, masonry, plumbing and complete pool transformations.
View Remodeling Services → Hardscape ConstructionExplore concrete, pavers, natural stone, walkways and coordinated hardscape construction.
View Hardscape Services → Drainage SolutionsLearn how grading and drainage can help manage water around pools and outdoor living areas.
View Drainage Solutions → Completed WorkBrowse completed pools, remodels, hardscape and outdoor-living projects.
Visit the Project Gallery → Questions and AnswersGet straightforward answers about planning, construction, materials and working with PLAPCO.
Read the FAQs →We begin with a phone conversation to understand the existing pool, surrounding hardscape, access, priorities and the scope you are considering.